Intermountain Rural Electric Association

The Intermountain Rural Electric Association (Intermountain REA) began to experience an increasing number of failures with cable laid in the in 1970s and ‘80s. By proactively rejuvenating entire neighborhoods before cables failed, the utility improved service levels to a 99.4 percent reliability rate and saved tens of millions of dollars.

London Hydro

London Hydro, Ontario, Canada

As an alternative to ongoing cable replacement, London Hydro asked Novinium to conduct a pilot cable injection project in a large subdivision. Since then, Novinium has gone on to inject more than 174,465 meters of cable for London Hydro and cable failures have declined by 58 percent.

Tacoma Power

Tacoma Power, Washington, U.S.A.

Some 4,800 feet of submarine cable from Tacoma Power, feeding 14 customers on tiny Ketron Island, was nearing the end of its design life. The utility decided to rejuvenate the underwater line before a fault occurred and has not experienced any faults in the now-guaranteed, rejuvenated cable.

Matanuska Electric Association (MEA)

MEA, Palmer, AK, U.S.A.

Matanuska Electric Association (MEA) found that even subdivisions with well-laid cable were experiencing increasing faults with the stress of multiple freezes each year, so the utility decided to try cable injection to restore reliable service. Now, the Novinium-trained MEA staff can do the work so efficiently that MEA plans to continue using cable injection year-round.

Greenwood Utilities

Greenwood Utilities, Greenwood MS, U.S.A

The Glendale Subdivision had experienced numerous faults—as many as five or six a year dating as far back as 1984. Greenwood Utilities hired Novinium to rehabilitate the utility’s vaults and treat the cable line in the area. After the project was finished, the subdivision experienced no faults.

City of St. Charles, IL

St. Charles Municipal Electric Utility

Estimated costs for the St. Charles Municipal Electric Utility cable replacement needs came in at about $6.6 million. St. Charles chose a solution comprised of 77 percent Novinium® cable rejuvenation and 28 percent cable replacement, saving $4.3 million, or 66 percent of the original project estimate.